Current Construction Projects

The projects and schedules are based on the program approved by Regional Council on January 11, 2017.

 

CAUTION AND DISCLAIMER: These projected capital works may change in nature, location or timing or may not occur at all as a result of changes in resources, priorities or other circumstances. These changes may occur prior to the start of the works or as the works are being carried out. AS A RESULT, THE REGIONAL MUNICIPALITY OF WATERLOO, ITS ELECTED OFFICIALS, OFFICERS, EMPLOYEES, CONTRACTORS AND AGENTS, WILL NOT ASSUME ANY RESPONSIBILITY OR LIABILITY FOR ANY COSTS, DAMAGES, LOSSES, LIABILITIES OR EXPENSES SUFFERED AS A RESULT OF THE USE OF OR RELIANCE UPON THIS INFORMATION.

 

 

Follow the links for a list of projects on regional roads in each municipality.

Cambridge

Kitchener

Waterloo

North Dumfries

Wellesley

Wilmot

Woolwich

*Note: Typical practice with reconstructing roads is to pave to base course asphalt, with surface course asphalt placed on the road the following year.

Cambridge

Name                         

Type of Work

Timing            

Details               

Contact          

Bishop Street (Reg. Rd. 41), Conestoga Blvd. to Concession Rd. Surface Asphalt May 2015 to Summer 2017  

Peter Linn

519-575-4757 x3773   

Cedar Street (Reg. Rd. 97), Osborne St. to Cambridge Boundary Reconstruction with Storm Sewers, Bike Lanes and Sidewalks Summer 2016 to Summer 2017 Link to Notice of Construction 

Ken Brisbois

519-575-4606

Coronation Boulevard(Reg. Rd. 8) at Cambridge Memorial Hospital Reconstruction Summer 2017  

Bill Gilbert

519-575-4603          

King Street (Reg. Rd. 8), Eagle St. to Fountain St. and Fountain Street (Reg. Rd. 8) King St. to Shantz Hill Rd. Road Widening with Bike Lanes and Sidewalks Spring to Fall 2017

Link to Information Sheet 

Jason Lane

519-575-4757 x3752

Fountain Street (Reg. Rd. 28), Blair Rd. to Dickie Settlement Rd. Resurfacing

October 2016 to December 2018

 

Luke Misurka

519-575-4738

Fountain Street (Reg Rd 28) Blair Road to Preston Parkway and Bridge at Grand River

Reconstruction and Bridge Replacement

October 2016 to December 2018

Link to Information Sheet 

John Stephenson

519-575-4096

Fountain Street (Reg. Rd. 17), King St. to Highway 401

Road Widening with Bike Lanes and Sidewalks

Spring to Fall 2017

Link to Notice of Construction 

Jason Lane

519-575-4757 x3752 

Franklin Boulevard (Reg. Rd. 36), Myers Rd. to  Hwy 401

Year 2 South - 125M South of Champlain Blvd to 200m South of Main St.

Year 2 North - 200m North of Clyde Road to 200m North of Avenue Road

Reconstruction with Roundabouts, Centre Median and Multi-Use Trails.

 

 

June 2017 to late summer 2018

 

April 2018 to late fall 2018

Current/ Upcoming Closures

Overall Project Phasing 

Year 2 South Aerial Photo 

Year 2 North Aerial Photo

Year 2 Notice of Tree Clearing and Utility Work

Year 2 South Tree Clearing Drawgings

Year 2 North Tree Clearing Drawings

Year 2 South Start of Construction Notice

Frank Kosa

519-575-4757 x3185

Franklin Boulevard Extension (Reg. Rd. 36) Myers Rd to South Boundary Road

South Boundary Road Hwy 24 (Water St) to Hwy 8 (Dundas St)

Phase 1A - Franklin from 125m South of Champlain Blvd to South City Limit

And - Bridge at South Boundary Road / Cheese Factory Road

Road Reconstruction, New Road Construction, Multi-Use Trails, New Bridge Construction Fall 2017 to end of 2018

Current and Upcoming Closures

Overall Project Phasing

Franklin Blvd Extension Preliminary Layout Plan

South Boundary Road Phase 1 Preliminary Layout Plan

Notice of Current Construction Timelines

Notice of Cheese Factory Road Closure

Notice of 1A Construction Start

Frank Kosa

519-575-4757 x3185

Franklin Boulevard (Reg. Rd. 36) Multi-Use Trail Connection Over Hwy 401 Multi-Use Trail    

Geoff Keyworth

519-575-4089

Roseville Road (Reg. Rd. 46) Turtle Crossing Drainage Improvement    

Luke Misurka

519-575-4738

Shantz Hill Road (Reg. Rd. 8), Fountain St. to Hwy 401 Eastbound Ramp Resurfacing with Sidewalks Spring to Fall 2017  

Jason Lane

519-575-4757 x3752 

St. Andrews Street (Reg. Rd. 75) at Grand Ridge Dr., Fourth Avenue and Southwood Drive Reconstruction Spring 2017 to Fall 2018 Link to Information Sheet

Ken Brisbois

519-575-4606

Water Street (Reg. Rd 24), 180m South of Myers Rd. to Myers Rd and 240m South of Ainslie St. South to Concession St./Cedar St. Resurfacing Summer 2017  

Luke Misurka

519-575-4738

Kitchener

Name                                  

Type of Work

Timing        

Details                 

Contact      

Courtland Avenue (Reg. Rd. 53) at Hayward Ave. (Reg. Rd. 67) Reconstruction with traffic signals   Details at RideION.ca

 

ION Telephone Line

1-844-625-1010

connect@rideion.ca

Fairway Road (Reg. Rd. 53), Hwy 8 Southbound Ramp to Wilson Ave. Sidewalks Summer 2017  

Luke Misurka

519-575-4738

Fischer-Hallman Road (Reg. Rd. 58), Bleams Rd. to Ottawa St. Road Widening with Sidewalks and Multi-Use Trail May 2016 to August 2017 Link to Notice of Construction 

Delton Zehr

519-575-4757

x3637

Highland Road (Reg. Rd. 6), West of Patricia Ave. to Westmount Rd. Surface Asphalt July 4th to July 15th, 2016  

Boris Latkovic

519-575-4457

King Street  (Reg. Rd. 15) at GEXR Crossing - Subway Installation Reconstruction   Details at RideION.ca

 

ION Telephone Line

1-844-625-1010

connect@rideion.ca

King Street (Reg. Rd. 15), Dixon Street/Montgomery Road to Ottawa Street Reconstruction May to November 2017 Link to Detailed Information

Dave Brown

519-575-4757 x3686

 King Steet (Reg Rd. 8), Fairway Road to Kinzie Avenue Resurfacing September to November 2017  Information Sheet

 Larry Van Wyck

519-575-4529

King Street East (Reg. Rd. 8), Fairway Rd. N. to Weber St. E. / Hwy 8 On-Ramp Reconstruction Summer 2017  

Larry Van Wyck

519-575-4529

Manitou Drive (Reg. Rd. 69), Homer Watson Blvd. to Bleams Rd. Reconstruction with Bike Lanes and Sidewalks Summer 2017 Link to Notice of Construction 

Larry Van Wyck

519-575-4529 

New Dundee Road (Reg. Rd. 12), Reidel Dr./Cameron Rd. to Fischer-Hallman Rd. Resurfacing with Bike Lanes

 Summer 2017

 

Boris Latkovic

519-575-4457

Ottawa Street, Elmsdale Drive to Imperial Drive Reconstruction, Two Roundabouts and Multi-Use Trails

April to October 2017

Link to Detailed Information

Wayne Cheater

519-575-4757 x3183

Ottawa Street (Reg. Rd. 4), Lackner Blvd. to Hwy 7 Eastbound Ramp  Reconstruction
and Road Widening with Cycling Lanes

Lackner Blvd to River Rd. - May - October 2016

River Rd. to Hwy 7 EB Ramp - May - October 2017

  

Link to Information Sheet 

Gary MacDonald

519-575-4721

Waterloo

Name                                 

Type of Work

Timing

Details         

Contact            

Allen Street (Reg. Rd. 37), Storm Sewer Replacement Storm Sewer Installation To Be Determined    
Bridge Street (Reg. Rd. 52) from 550m Sough of Northfield Dr. to Northfield Drive Storm Sewers, Curb and Gutter and Multi-Use Trail Summer 2017  

Luke Misurka

519-575-4738

Erbsville Road (Reg. Rd. 70) at Columbia St. Reconstruction Spring - Fall 2017  

Marcos Kroker

519-575-4750

City of Waterloo

519-886-2310

Erb Street (Reg. Rd. 9) at Westmount Road (Reg. Rd. 50) Reconstruction 2017  

Larry Van Wyck

519-575-4529

Erb Street (Reg. Rd. 9), 100m East of Caroline St. to Menno St. Reconstruction with Storm Sewers and Bike Lanes To Be Determined  

Bill Gilbert

519-575-4603 

King Street (Reg. Rd. 15), North of Weber Street to Highway 85 Surface Asphalt Summer - Fall 2017  

Eric Saunderson

519-575-4746

King Street North (Reg Rd. 15), University Avenue to ION tracks south of Erb Street Reconstruction, Cycling Lanes, Sidewalks April to October 2017 Link to Detailed Information Sheet

Eric Saunderson

519-575-4746

Weber Street (Reg. Rd. 8), Erb Street to University Avenue  Resurfacing 2017  

Larry Van Wyck

519-575-4529

Westmount Road (Reg. Rd. 50) at University Ave. Bridge Improvements Spring to Summer 2017  

Ken Brisbois

519-575-4606

Westmount Road (Reg. Rd. 50), John Street to Erb Street Resurfacing and Sidewalks 2017  

Larry Van Wyck

519-575-4529

North Dumfries

Name

Type of Work

Timing            

Details         

Contact                  

New Dundee Road (Reg. Rd. 12), Reidel Dr./Cameron Rd. to Fischer-Hallman Rd. Resurfacing with Bike Lanes Summer 2017

 

Boris Latkovic

519-575-4457

Trussler Road (Reg. Rd. 70), 110m North of Hwy 401 to Cedar Creek Rd. and Brant/Waterloo Rd. to Greenfield Rd. Resurfacing with Bike Lanes Spring to Fall 2017

 

Boris Latkovic

519-575-4457

Trussler Road (Reg. Rd. 70), at Nith River Bridge (North and South) Bridge Improvements Spring to Fall 2017

 

Ken Brisbois

519-575-4606

 

 

Wellesley

Name

Type of Work

Timing

Details

Contact                 

Hutchison Road (Reg. Rd. 5), Crosshill S. Limits to Crosshill W. Limits Reconstruction with Bike Lanes and Sidewalks Spring 2017 Link to Notice of Construction 

Peter Linn

519-575-4757

x3773

Line 86 (Reg. Rd. 86), Conestogo River Bridge Bridge Improvements and Bike Lanes May to October 2016  

John Stephenson

519-575-4096

 

Wilmot

Name

Type of Work

Timing

Details

Contact                 

Notre Dame Drive (Reg. Rd. 12) and Snyder's Road East (Reg. Rd. 6), Petersburg  Reconstruction April to October 2017 Link to Information Sheet

 Ian Young

519-575-4757 x3079

Wilmot Easthope Road (Reg. Rd. 1) Huron Rd to 50m South of Hwy 7/8 Resurfacing with Bike Lanes  2017  

Boris Latkovic

519-575-4457

 

Woolwich

Name

Type of Work

Timing

Details

Contact               

King Street (Reg. Rd. 8), Pintery Rd. to Sawmill Rd. Reconstruction with Bike Lanes and Sidewalks Spring 2016 to Summer 2017

Construction Closure Letter

Link to Notice of Construction Letter No. 2

Link to Notice of Construction Letter No. 1 

Link to Preconstruction Information Sheet 

Link to Preconstruction Information Presentation Slides 

Ian Young

519-575-4757

x3079

Sawmill Road and Northfield Drive,Village of Conestoga Reconstruction April 3, 2017 to November 30, 2017 Link to Project Information Sheet

Jim Ellerman

519-575-4757

x3757

 

 