Construction notice: Church Street East Improvements Elmira, April 29–17, 2024
About the project
The final phase of this construction will include repairs, landscaping, surface asphalt, and line markings
Timing — April 29 to May 17, 2024
- Sidewalk, curb and gutter repairs, stone cladding on the Bridge Parapet walls, and landscaping. Minor underground work at Duke St/Church Street intersection, final surface paving and pavement markings.
Closures
Church Street East — May 13 — 17, 2024
- Church Street East will be closed to through traffic between Duke Street and George Street.
- Two-way traffic will be maintained between Arthur Street and Riverside Drive, as well as George Street and Northfield Drive.
Church Street East — week of May 20, 2024
- Church Street East will be closed for one day during this week for asphalt work.
Detour — May 13 — 17, 2024
- Northfield Drive— Sawmill Road—Arthur Street
- Residents east of the Bridge, including George, High, and Charles Streets will need to travel east to Northfield Drive.
- Emergency Services (Police, Fire, Paramedics), student transportation, and waste collection have been notified of the construction, closures, and detours to minimize any disruptions to services.
- The road will be reopened on Friday, May 17, 2024.
Pedestrian access
The sidewalks in this area will remain accessible during the project. Pedestrians should follow the signs as they walk through the site. Pedestrians should also be mindful of sidewalk panels that have been blocked off due to freshly poured concrete and avoid walking those individual panels to allow the concrete to dry properly.
Property and business access
All businesses in the area remain open and accessible during construction.
Every effort will be made to maintain access to residential and business driveways in the construction area during working hours (7 a.m.–7 p.m.). Construction activities may temporarily impact access to entrances. We will provide notice of any interruption in advance as much as possible. Home Hardware to be accessed from Duke Street.
Please plan for some delays and travel carefully in the construction zone. We request that when driving or walking through and around the construction zone you follow and obey the construction traffic signage for your safety and the safety of the workers.
More information
Region’s Service First Contact Centre: 519-575-4400 or visit the project page for additional information including contact phone numbers and emails.
Contact Us