Fischer-Hallman Road | Bleams to Plains

Overview

Project number: 07122 |  Updated: February 2025

The Region of Waterloo is improving Fischer-Hallman Road between Bleams Road and Plains Road in Kitchener.

This work includes:

  • Widening to four lanes with a raised centre median
  • Two new roundabouts at Rosenberg Way and Wallaceton Way
  • Multi-use paths on each side of the road
  • Water and storm sewer underground infrastructure installation
  • New street lighting and bus stop pads
  • Wildlife passage culvert and fencing

This project is being completed in phases:

  • Phase 1: Bleams Road to approx. 150 metres north of Rosenberg Way
  • Phase 2: Approx. 150 metres north of Rosenberg Way to 750m north of Seabrook Drive, including roundabouts at Wallaceton Way and Rosenberg Way
  • Phase 3: Approx. 750m north of Seabrook Drive to Huron Road and south of Haldimand Street to south of Plains Road

Schedule

Environmental assessment: 2015–2016
Design and planning: 2016–2025
Construction phase 1: 2020–2021 (completed)
Construction phase 2: 2023–2024 (completed)
Construction phase 3: 2026

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

Phase 3: $10,645,000

Contact

Adam Galezowski, P.Eng.
Engineer, Region of Waterloo
AGalezowski@regionofwaterloo.ca 

Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608


Public engagement

The public was invited to provide feedback on this project during the environmental assessment process in 2015 and 2016. See details from that engagement below.


Project details

Project studies and resources

Project planning and studies

 Council and Committee reports

Additional notes

This project supports the Region of Waterloo's strategic focus areas(External link)Climate aligned growthHomes for allEquitable services and opportunities.