Construction notice: Regional pavement repairs, August–September 2025

About the project

The Region of Waterloo will be repairing damaged asphalt at 90 locations across the region over the next two months. This process includes removing the top layer of asphalt, cleaning, applying a tack coat to keep the asphalt layers together, and resurfacing with new asphalt and road lines. 

Timing 

Construction will be completed in phases across each location from August 18 to September 26, 2025. Crews will make lane repairs on the road surfaces in Phases 1 and 2 and return to narrow but longer repairs in Phase 3.

Location

Phase 1 and 2

Phase 3

Township of Wellesley

August 18 to August 22

 

Township of Woolwich

August 21 to August 26

 

Township of Wilmot

August 25 to August 27

 

Kitchener and Waterloo

August 28 to September 15

September 23

Cambridge and North Dumfries

September 10 to September 22

September 24 to September 26

View the map of the repair locations here.

Lane reductions

Traffic will be maintained throughout all construction locations. There may be periods where traffic will be delayed. The crew will be onsite to direct traffic as needed. 

Pedestrian access

The sidewalks will remain accessible during each project. Pedestrians should follow the signs as they walk through the site.

Property and business access

All businesses in the construction area remain open and accessible during construction. Every effort will be made to maintain access to residential and business driveways in the construction area during working hours (7 a.m.–7 p.m.). Construction activities may temporarily impact access to entrances. We will provide notice of any interruption in advance as much as possible.

Contact information