Project number: 05654 | Updated: May 2026
The Region is planning road and bridge improvements on Maryhill Road from St. Charles Street to the Waterloo/Wellington boundary in the Township of Woolwich.
The underground infrastructure, road surface, and bridge need to be upgraded, as they have reached the end of their service life. The Region is also improving pedestrian facilities including new and extended sidewalks and pedestrian crossings.
Schedule
Design and planning: 2026–2027
Construction: 2027 and 2028
Note: Construction timelines are an estimate and are subject to change.
Budget
$4.68 million
Contact
Eric Saunderson, P.Eng, PMP
Senior Engineer, Region of Waterloo
ESaunderson@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Public engagement
Residents and stakeholders are invited to attend an in-person public engagement session to learn more about the project, review the preferred design, and provide feedback.
Location: Maryhill Heritage Park Community Centre
Date: May 27, 2026
Time: 5 p.m. – 7 p.m.
Project information and an online survey can be accessed through the EngageWR project page. Feedback can be submitted between May 27 to June 10, 2026.
Project details
This project supports the Region of Waterloo's strategic focus areas: Climate aligned growth.