Project number: 05654 | Updated: March 2026
The Region is planning road and bridge improvements on Maryhill Road from St. Charles Street to the Waterloo/Wellington boundary in the Township of Woolwich.
The underground infrastructure, road surface, and bridge need to be upgraded, as they have reached the end of their service life. The Region is also improving pedestrian facilities including new and extended sidewalks and pedestrian crossings.
Schedule
Design and planning: 2026–2027
Construction: 2027 and 2028
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
$4.68 million
Contact
Eric Saunderson, P.Eng, PMP
Senior Engineer, Region of Waterloo
ESaunderson@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Public engagement
The public will have the opportunity to learn about the preferred design for this roadway and provide their feedback in spring 2026. Get involved through the EngageWR project page.
Project details
This project supports the Region of Waterloo's strategic focus area: Climate aligned growth
Contact Us