Scheifele Bridge

Overview

Project number: 05954 | Updated: October 2026

At a glance

The Region of Waterloo is replacing the Scheifele Bridge in Woolwich, located on Northfield Drive over the Conestogo River.

Construction: Summer 2026–2028
Budget: $24 million
Current status: Construction underway
Road: Northfield Drive remains open in both directions
Pedestrians: Access across the bridge maintained
Cyclists: Use alternate routes during construction

 

The Region of Waterloo is replacing the Scheifele Bridge on Northfield Drive over the Conestogo River.

An environmental assessment was completed between 2021 and 2023 to determine the most practical and cost-effective approach to replacing the bridge and accommodating future traffic volumes, pedestrians, buggies and cyclists.

The new bridge will include:

  • Paved shoulders for buggies and cyclists on both sides of the bridge
  • A sidewalk on the east side
  • A concrete barrier separating pedastrians from traffic

View the bridge design
View the project map

The bridge is being replaced to:

  • accommodate future traffic volumes;
  • improve facilities for pedestrians, buggies and cyclists; and
  • replace the existing bridge with a new structure designed to meet current and future needs.

Northfield Drive will remain open in both directions for most of the construction period as the work will be completed in stages. Some short-term closures may be required over the three construction seasons to safely complete certain portions of the work. If any closures are needed, residents will be notified in advance, and detour routes will be clearly communicated. 

Pedestrian access across the bridge will be maintained throughout construction. However, due to narrow lanes, cyclists will be asked to use alternate routes, including University Avenue, Country Squire Lane, Country Squire Road, Glasgow Street, and Sawmill Road, during construction. When walking or cycling through the construction zone, please follow and obey all posted signage for your safety.  

Over the coming months, crews will continue foundation work for the new bridge. In-water work is tentatively expected to be completed in December, followed by the removal of some temporary causeway material for the winter and spring.

Construction will continue through the winter when weather and site conditions allow.

Schedule

Environmental assessment 2021–2023

Design and planning Spring 2024–Winter 2025

Site preparation December 2025–April 2026

Construction Summer 2026–2028 (ongoing)

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Contact

Ken Brisbois, C.Tech.
Project Manager, Region of Waterloo
kbrisbois@regionofwaterloo.ca 

Service First Contact Centre: 519-575-4400

Public engagement

The public was encouraged to provide input on this project during the environmental assessment from 2021 to 2023. For more details on that engagement, visit the EngageWR project page.

Contact Us

Region of Waterloo HQ
150 Frederick St.
Kitchener, Ontario N2G 4J3
Telephone: 519-575-4400
Fax: 519-575-4481

For general inquiries:
Regionalinquiries@regionofwaterloo.ca

Other Main Region Locations

Cambridge Main Office
150 Main St.
Cambridge, ON N1R 6P9

Waterloo Main Office
99 Regina St. S.
Waterloo, ON N2J 4V3