New Dundee Road

On this page:


Pinnacle Drive to Reichert Drive

Project number: 07284 |  Updated: August 2026

The Region of Waterloo has completed the construction on New Dundee Road between Reichert Drive and Pinnacle Drive in Kitchener. This work included:

  • Installing a new roundabout
  • Adding new eastbound and westbound left-turn lanes
  • Widening the road to include paved shoulders
  • Installing new multi-use paths and pedestrian handrails
  • Installing new underground storm sewer, sanitary sewer and watermain infrastructure

Schedule

Design and planning: 2022
Construction (phase 1): Summer - Fall 2025 
Construction (phase 2): June 2026 - July 2026

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Getting around during construction

Construction on New Dundee Road between Reichert Drive and Pinnacle Drive in Kitchener has now been substantially completed

Text NWDE to 57555 to receive the latest updates on the project. Standard messaging rates apply.

Budget

$4,087,000

Contact

Romeo Uy, P.Eng.
Project Manager, Region of Waterloo
ruy@regionofwaterloo.ca

Service First Contact Centre: 519-575-4400


Fischer-Hallman Road at New Dundee Road

Project number: 05284 |  Updated: July 2026

The Region of Waterloo is installing a roundabout at the intersection of New Dundee Road and Fischer-Hallman Road, located at the boundary between the City of Kitchener (north side) and the Township of North Dumfries (south side). The work includes: 

  • Installation of storm sewers
  • Installation of a base layer of the road
  • Curb and gutter
  • Asphalt removal and replacement
  • New ditch grading and profiling 
  • Additional street lighting within the project limits.

This decision is based on technical studies and input received from the public through engagement in 2022. 

Schedule

Design and planning: 2022
Detailed design: 2024–2025
Construction: July - November 2026

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

$2,957,000

Getting around during construction

The project is being completed in three stages to reduce traffic impacts throughout construction. Construction began on July 2, 2026. Stage 1 has been completed. 

Beginning July 27, Stage 2 of construction will be in place for approximately 8 weeks and will include the closure of the north leg of Fischer-Hallman Road at the intersection. The roundabout will operate as a three-way stop, with access to the work area limited to local traffic only.

During this stage, construction activities will include asphalt removal and underground storm sewer installation. Following Stage 2, construction will transition to Stage 3, which will include the closure of the south leg of the intersection. Local access and traffic movements will be maintained where possible throughout construction.

Detours will be in place during Stages 2 and 3. During Stage 2, southbound traffic on Fischer-Hallman Road will be redirected via Huron Road and Trussler Road. During Stage 3, eastbound traffic on New Dundee Road will be detoured via Trussler Road and Cedar Creek Road. 

During construction, traffic may occasionally be required to travel on a gravel surface and may be controlled by traffic control staff.

Contact

Steve Yonemitsu, P.Eng.
Project Manager, Region of Waterloo
syonemitsu@regionofwaterloo.ca

Service First Contact Centre: 519-575-4400

Contact Us

Region of Waterloo HQ
150 Frederick St.
Kitchener, Ontario N2G 4J3
Telephone: 519-575-4400
Fax: 519-575-4481

For general inquiries:
Regionalinquiries@regionofwaterloo.ca

Other Main Region Locations

Cambridge Main Office
150 Main St.
Cambridge, ON N1R 6P9

Waterloo Main Office
99 Regina St. S.
Waterloo, ON N2J 4V3