- Construction notice (June 2026)
Manser Road Watermain
Overview
Project number: 04082 | Updated: June 2026
The Region of Waterloo will be installing a new watermain along Manser Road, from south of Lin Dunn Lane to North of Lin Dunn Lane to improve the capacity of the local water distribution system
Schedule
Design and planning: 2025–2026
Construction: July 2026 - September 2026
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
$444,000
Getting around during construction
Two-way traffic will be maintained on Manser Road for the duration of construction. Access to driveways will be maintained as much as possible during work and at the end of each day.
Contact
Chris Gatchene, C.E.T
Supervisor Infrastructure Renewal, Region of Waterloo
CGatchene@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Project details
View the project map