Ottawa Street | Fischer-Hallman to Mowat
Overview
Project number: 05796 | Updated: March 2026
The Region of Waterloo is improving Ottawa Street from Fischer-Hallman Road to Mowat Boulevard in Kitchener.
Phase 1: Fischer-Hallman Road to Pinedale Drive
- Reconstructed the intersection to be more pedestrian and cyclist friendly including shortening the distance of crossings, added pedestrian islands and raised the crosswalk on the right-turn lane going into Sunrise Plaza.
- Added multi-use paths on Ottawa Street
- Upgraded underground infrastructure including new electrical, water main and storm sewers
- Reconfigured the right-turn lane from Fischer-Hallman to Ottawa so all drivers now yield to oncoming traffic and then merge
Phase 2: Pinedale Drive and Mowat Boulevard
- Constructing a new roundabout at the Ottawa Street and Westmount Road intersection
- Multi-use paths continuing on Ottawa Street
- Replacing the Moffat Creek Culvert and watermain
- Upgrading storm sewers
Schedule
Design and planning: 2019–2022
Construction phase 1: 2024
Construction phase 2: April–December 2025
Asphalt paving: 2026
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
$10,200,000
Contact
Jason Guan, P.Eng.
Project Manager, Region of Waterloo
JGuan@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Contractor
Capital Paving
Getting around during construction
Text 57555 with the code OTWA to get the latest information on the project.
Closures
A one-day road closure of the roundabout will be in place on May 13 at:
- South-west corner at the roundabout at Ottawa Street South and Westmount Road
- Eastbound traffic on Ottawa Street and southbound traffic on Westmount Road will be closed
This closure is required to survey and inspect the existing overhead telecommunication cables for relocation.
A second phase of work is planned for early June, which will require a two-day full closure of the entire roundabout. More details will be shared in advance.
Project studies and resources
- Planning and works committee report (December 2019)
- Council report (May 2024)
- Construction notice phase 1 (May 2024)
- Construction notice phase 2 stage 1 (March 2025)
- Construction notice phase 2 stage 2 (July 2025)
This project supports the Region of Waterloo's strategic focus area: Climate aligned growth and Equitable services and opportunities.