Ottawa Street | Fischer-Hallman to Mowat
Overview
Project number: 05796 | Updated: July 2026
The Region of Waterloo is improving Ottawa Street from Fischer-Hallman Road to Mowat Boulevard in Kitchener.
Phase 1: Fischer-Hallman Road to Pinedale Drive
- Reconstructed the intersection to be more pedestrian and cyclist friendly including shortening the distance of crossings, added pedestrian islands and raised the crosswalk on the right-turn lane going into Sunrise Plaza.
- Added multi-use paths on Ottawa Street
- Upgraded underground infrastructure including new electrical, water main and storm sewers
- Reconfigured the right-turn lane from Fischer-Hallman to Ottawa so all drivers now yield to oncoming traffic and then merge
Phase 2: Pinedale Drive and Mowat Boulevard
- Constructing a new roundabout at the Ottawa Street and Westmount Road intersection
- Multi-use paths continuing on Ottawa Street
- Replacing the Moffat Creek Culvert and watermain
- Upgrading storm sewers
Schedule
Design and planning: 2019–2022
Construction phase 1: 2024
Construction phase 2: 2025 - 2026
Asphalt paving: 2026 - 2027
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
$10,200,000
Getting around during construction
Text OTWA to 57555 to receive the latest information on the project. Standard messaging rates apply.
Closures
A one-day closure will be in place on August 5 at the southwest quadrant of the Ottawa Street South and Westmount Road roundabout.
During the work, the affected section of the roundabout will be closed for up to two minutes at a time, followed by a one-hour reopening period. This cycle will repeat throughout the day.
Please plan ahead and expect delays.
Contact
Jason Guan, P.Eng.
Project Manager, Region of Waterloo
JGuan@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Contractor
Capital Paving
Project studies and resources
- Planning and works committee report (December 2019)
- Council report (May 2024)
- Construction notice phase 1 (May 2024)
- Construction notice phase 2 stage 1 (March 2025)
- Construction notice phase 2 stage 2 (July 2025)
This project supports the Region of Waterloo's strategic focus area: Climate aligned growth and Equitable services and opportunities.