Highway 7/8 Pedestrian Bridge

Overview

Project number: 66114 | Updated: May 2025

Construction of a pedestrian and cycling bridge has been installed over Highway 7/8 connecting Avalon Place to Chandler Drive/Strasburg Road. The new bridge can be accessed through a ramp or staircase on each side and is met with new sidewalk along the south side of Avalon Place and a multi-use path along Strasburg Road to Ottawa Street. Final landscaping work and finishing touches will be completed this summer.

Schedule

Environmental assessment: 2016–2018
Design and planning: 2018–2022
Construction: Spring 2022–Spring 2025
Landscaping and final touches: Summer 2025

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget 

$9.5 million

Contact

Andrew Doman, Senior Engineer
Project Manager, Region of Waterloo
adoman@regionofwaterloo.ca

Service First Contact Centre: 519-575-4400

Contractor

Eiffage GC Canada


Project details

Project studies and resources

 Project planning and studies
 Committee and Council reports
 Construction activities

Additional notes

Construction for the bridge began in 2022 and was delayed due to supply chain shortages across the country. 

This project supports the Region of Waterloo's strategic focus areas(External link)Climate aligned growth and Equitable services and opportunities.