Arthur Street

Overview

Project number: 05394 |  Updated: March 2026

The Region of Waterloo is improving Arthur Street from Kenning Place to South Street E in Elmira. This section of Arthur Street includes the downtown core of Elmira and approximately 940 meters north of Church Street, including the Canagagigue Creek bridge. The underground infrastructure, road, sidewalks and bridge need to be upgraded, as they have reached the end of their service life.

Phase 1 of this project from South Street E to Church Street will include asphalt resurfacing, replacement of existing sidewalks, removal of brick paving stones, and upgrades to streetlighting. No cycling lanes will be added. This phase will not include the Arthur Street and Church Street intersection.

Phase 2 of this project from Church Street to Kenning Place is still being planned and designed.

Schedule

Design and planning: 2021–2026
Construction phase 1: 2026
Design and planning of phase 2: 2026–2027
Construction phase 2: 2028

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

Phase 1: $2.5 million

Contact

Boris Latkovic, P.Eng, PMP
Senior Engineer, Region of Waterloo
Blatkovic@regionofwaterloo.ca

Service First Contact Centre: 519-575-4400


Public engagement

Thank you to everyone who shared their input on this project. We appreciate the time and thoughtful feedback provided by residents, businesses, and community members. Based on community input and Township and Regional Council directive, Arthur Street from South Street E to Church Street will get rehabilitated in the 2026 construction season. 

Phase 2 of this project between Church Street and Kenning Place (including the Canagagigue Creek bridge) will continue in the design and planning stage. Stay up to date on that work on the EngageWR project page.

EngageWR – Get involved


Project details

This project supports the Region of Waterloo's strategic focus area: Climate aligned growth

Strategic Plan graphic