Project number: 04083 |  Updated: November 2025

The Region of Waterloo is installing a new watermain along Fountain Street North 850m south of Flanders Road in Woolwich. During this work the asphalt, shoulders and boulevards will also be replaced. 

This project aims to improve the water supply system in the Township of Woolwich and support the growing community.

Schedule

Design and planning: 2024–2025
Construction phase A and B: September–December 2025 (weather permitting)
Construction phase C: Spring–Fall 2026 (subject to permits and rail coordination)
Final restoration: Late 2026

Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.

Budget

$8.7 million

Contact

Padraig Keating, P.Eng, P.M.P.
Senior Engineer, Region of Waterloo
PaKeating@regionofwaterloo.ca

Service First Contact Centre: 519-575-4400

Text 57555 with the code FNTN to get the latest information on the project.


Getting around during construction

Construction is now finished for 2025. Work will begin again in spring 2026. Advance notice of construction impacts will continue to be shared on this webpage.


Project details

Project studies and resources

 Project planning and studies
 Construction activities

Additional notes

This project supports the Region of Waterloo's strategic focus area(External link)Climate aligned growth and Homes for all.

Strategic Plan graphic

Contact Us