New Dundee Road
On this page:
- Pinnacle Drive to Robert Ferrie Drive
- Dodge Drive W to Dodge Drive E
- Fischer-Hallman Road at New Dundee Road
Pinnacle Drive to Robert Ferrie Drive
Project number: 07284 | Updated: January 2025
The Region is improving New Dundee Road in Kitchener. Phase 1 was completed in 2024, which was from 70m east of Executive Place to Pinnacle Drive. Phase 2 will work on Pinnacle Drive to Robert Ferrie Drive. This work will include water, storm and sanitary servicing, road reconstruction and a new multi-use path on the north side of the road.
Phase 2 will also include a new roundabout at the New Dundee Road and Robert Ferrie Drive intersection.
Schedule
Design and planning: 2022
Construction phase 1: Completed in 2024
Construction phase 2: Summer—Fall 2025
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
Phase 1: $1,500,000
Phase 2 roundabout: $4,087,000
Contact
Romeo Uy, P.Eng.
Project Manager, Region of Waterloo
ruy@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608
Project resources and studies
Project planning and studies |
|
Committee and Council reports |
|
Dodge Drive W to Dodge Drive E
Updated: January 2025
This section of New Dundee Road is being worked on by Cachet Developments (New Dundee) Inc. as they are developing a new subdivision with 127 units of condominium townhouses at 1000 New Dundee Road. This new development requires municipal servicing including local sanitary sewer and a watermain connection and full road reconstruction.
Schedule
Design and planning: 2024
Construction: Spring–Fall 2025
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Contact
Romeo Uy, P.Eng.
Project Manager, Region of Waterloo
ruy@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608
Fischer-Hallman Road at New Dundee Road
Project number: 05284 | Updated: January 2025
The Region is constructing a partial two-lane roundabout at the New Dundee Road and Fischer-Hallman Road intersection in North Dumfries. This decision is based on technical studies and input received from the public through engagement in 2022.
Southbound: Through right turn lane and left turn lane
Westbound: Through left turn lane and a right turn lane
North and southbound: Single lanes
Schedule
Design and planning: 2022
Construction: Summer 2025 (tentative)
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
From the Transportation Capital Plan: $2,957,000
Contact
Steve Yonemitsu, P.Eng.
Project Manager, Region of Waterloo
syonemitsu@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400; for deaf and hard of hearing (TTY) call 519-575-4608
Project resources and studies
Project planning and studies |
|