- Construction notice (June 2026)
Can-Amera Parkway
Overview
Project number: 07194 | Updated: July 2026
The Region of Waterloo is improving Can-Amera Parkway between Conestoga Boulevard and Franklin Boulevard in Cambridge. These improvements include:
- Asphalt pavement replacement
- New multi-use path on both sides of the roadway (3.0m wide)
- GRT bus stop improvements
- New street lighting within the project limits
- Guiderail replacement along the north side of the road
Schedule
Design and planning: 2025–2026
Construction: July 2026 - August 2026
Note: timing may be affected by weather conditions and changing project scope; updates will be posted as needed.
Budget
$2.72 million
Getting around during construction
Can-Amera Parkway will remain open to two lanes of through traffic for the duration of construction, except for a few short-term full road closures to accommodate certain portions of the work, including surface asphalt placement.
There may be periods during construction when traffic will need to travel on temporary asphalt pavement, as well as times when traffic will need to be controlled with flag persons.
For information on impacts to GRT bus routes including stop changes and closures, visit GRT alerts.
Contact
Karolina Krol, P.Eng
Engineer, Region of Waterloo
kkrol@regionofwaterloo.ca
Service First Contact Centre: 519-575-4400
Project details
Project studies and resources
This project supports the Region of Waterloo's strategic focus areas: Climate aligned growth.